fbpx

Ecological closure Cell I Bacau - Environmental protection

At Inoveco, every environmental project is more than just a technical job - it's a concrete step towards protecting the planet and communities. In this spirit, we are committed to finalizing the ecological closure of Cell I Bacau of the Bacau non-hazardous waste landfill.

Where and how we work

The warehouse is located in Bacau, on Chimiei street, on an area of 324.830 square meters. Cell I has 5.17 ha, a volume of 855,000 cubic meters and a height of 40 meters.

The landfill has reached its capacity and storage activities have ended. According to environmental legislation and common environmental sense, the site must be greened and closed to prevent pollution and protect the health of local people.

Our project about the ecological closure of cell I Bacau follows a circular economy model, and this means that:

  • Reduce the amount of waste generated;

  • We recycle and reuse as much as possible;

  • We neutralize and isolate existing waste according to EU standards.

Ecological closure Cell I Bacau - greening stages

Stage 1 - Initial works and monitoring

The first stage lasts five months, plus 3-5 years of subsidence monitoring. We lay the foundation for the ecological works, systematize the site, rehabilitate the degassing system and closely monitor the interventions throughout the entire period of subsidence.

Stage 2 - Final closure and supervision

The second phase, lasting ten months, involves the realization of the complete closure system of Cell I, the collection and evacuation of rainwater, the drilling of boreholes for groundwater monitoring and the continuation of site surveillance to intervene quickly if the need arises.

Project benefits for the community

With our expertise in environmental infrastructure, we ensure that:

  • The risk of soil, water and air pollution is eliminated;

  • The project complies with EU legislation and standards;

  • The population in the area is protected;

  • The place is harmoniously integrated into the natural circuit after closing.

Inoveco's commitment to the environment

We are starting the works with the relocation of 25,000 cubic meters of waste for the geometrization of the landfill and 30,600 cubic meters of soil for the supporting layer. We will also connect 13 biogas wells to the combustion plant. This project is not just about concrete, membranes or degassing. It's about responsibility, sustainability and respect for the environment. And we are proud that we can contribute to a cleaner future for Bacau.